If you operate an electricity or gas installation and it is connected to an electricity or gas grid, you must register the unit in the Market Master Data Register (MaStR) of the Federal Network Agency. You only have to register plants in planning in certain cases.
As the central register for the energy transition, the Market Master Data Register (MaStR) records data on all generation plants:
If you operate an electricity or gas generation plant (for example, photovoltaic plant, wind energy plant, combined heat and power plant, battery storage, biomethane plant), you must register it in the MaStR. You are also obliged to register if no subsidy is granted or claimed for the electricity from the plant.
All running plants must be registered regardless of when they were commissioned - even if your plant has been running for many years. This means that even if you have already registered your plant in various other places, for example with your grid operator or in earlier registers of the Federal Network Agency, you must register these plants again in the MaStR.
If an installation is shut down, you must also report this in the register. If the installation is not connected to any electricity or gas grid, no notification is required.
To ensure that payments under the Renewable Energy Sources Act (EEG) or the Combined Heat and Power Act (KWKG) are paid out without deductions, you must comply with the registration deadlines set by the legislator.
You must register via the Federal Network Agency's Internet portal.
As a citizen, you can also register via forms in exceptional cases.
Authorities can access the MaStR data. This enables them to either significantly simplify their own surveys or dispense with them altogether. Plant operators and other market players can refer to the data they have entered in the MaStR.
You do not have to meet any prerequisites.
The information required for registration can be found in the following documents:
If you would like to register yourself as an operator and your electricity and gas generation plants in the MaStR, you can do so via the MaStR Internet portal:
You don't have to pay anything.
You must register within 1 month of the occurrence of an event requiring registration.
There is no provision for appeal.
If you are a market player in the electricity or gas market, you must register in the Market Master Data Register (MaStR) of the Federal Network Agency.