Immission control; notification of the commissioning of a fixed installation requiring a permit for the transfer or storage of fuels

Do you want to commission a stationary facility for transferring or storing fuels that does not require a permit? Then you must notify the competent authority in advance.

Responsible for you

For contact details of the responsible authoritiy and local valid information select under "Select location" a location.
Stilisiertes Bild eines Hauses
Kreisverwaltungsbehörden
Mehr zur Behörde

Procedure details

If you wish to commission a stationary installation for the transfer or storage of petrol, fuel mixtures or raw petrol that does not require a permit, you must notify the competent authority in advance.
Installations that do not require a permit are those that do not have to undergo a permit procedure as defined by the Federal Immission Control Act.

You wish to put into operation a stationary installation for the transfer or storage of petrol, fuel mixtures or raw petrol that does not require a permit.

  • Required document/s

    Completed advertisement

  • You submit your report to the authority responsible for you.
  • The competent authority checks your notification.
  • If necessary, the competent authority will contact you for further information

There are no costs.

You must submit the notification prior to the intended commissioning of the system.

There is no processing deadline.

If you do not make the report, do not make it correctly or do not make it on time, you are committing an administrative offense.

None. The administrative service is a real act against which no legal remedy is possible.

Status: 20.01.2026