Would you like to carry out an emission-relevant modification to a medium-sized combustion plant, gas turbine or combustion engine plant? Then you must notify the responsible immission control authority.
If you wish to carry out an emission-relevant change to a medium-sized combustion plant, gas turbine or combustion engine plant, you must notify the responsible immission control authority in advance.
The obligation to notify generally applies to all combustion plants with a rated thermal input of at least 1 MW and less than 50 MW, whether or not they require a permit.
In the case of aggregated combustion plants, you must notify the planned commissioning if the combined rated thermal input is more than 1 MW and less than 50 MW.
The authority responsible for you will then enter the information you provide in a register of installations, which is publicly accessible.
You would like to carry out an emission-relevant modification to a medium-sized combustion, gas turbine or internal combustion engine system.
Complete written or electronic notification
There are no costs.
The emission-relevant modification of an installation must be reported immediately, but at the latest within one month.
There is no deadline for processing.
You are committing an administrative offense if you do not submit the notification, or do not submit it correctly, completely, in the prescribed manner or on time.
None. The administrative service is a real act against which no legal remedy is possible.
Do you want to commission a medium-sized combustion, gas turbine or internal combustion engine plant? Then you must notify the responsible immission control authority.
If you operate a medium-sized combustion plant, gas turbine or internal combustion engine plant, you must notify the competent authority.