If you wish to commission a direct current system or a low-frequency system with a rated voltage of 110 kilovolts or more, you must notify the competent authority.
If your system does not require any other official permits relating to immission control, you must notify the responsible authority of the commissioning. You have at least 2 weeks before commissioning to do this.
If you want to commission a low-frequency system with less than 110 kilovolts, you only have to submit the necessary documents if the competent authority requests you to do so.
There are no costs.
You must have submitted the notification to the competent authority at least two weeks before commissioning the system.
There is no statutory processing period.
You must have submitted the notification to the responsible authority at least 2 weeks before commissioning the system. The notification will be processed as soon as it is received.
If you do not submit the notification, or do not submit it correctly, completely or on time, you are committing an administrative offense.
None . As this is only a notification procedure, no legal action is possible on your part.