Immission control; notification of the commissioning of a low-frequency or direct current system

If you wish to commission a direct current system or a low-frequency system with a rated voltage of 110 kilovolts or more, you must notify the competent authority.

Responsible for you

For contact details of the responsible authoritiy and local valid information select under "Select location" a location.
Stilisiertes Bild eines Hauses
Kreisverwaltungsbehörden
Mehr zur Behörde
Stilisiertes Bild eines Hauses
Regierungen
Mehr zur Behörde
Stilisiertes Bild eines Hauses
Bergämter
Mehr zur Behörde

Procedure details

If your system does not require any other official permits relating to immission control, you must notify the responsible authority of the commissioning. You have at least 2 weeks before commissioning to do this.

If you want to commission a low-frequency system with less than 110 kilovolts, you only have to submit the necessary documents if the competent authority requests you to do so.

  • Your installation crosses or is located
    • on a property in the area of a development plan or
    • within a built-up district or
    • on a plot of land with residential buildings in an outdoor area.

  • Required Documents
    • Display with the relevant data for the system
    • Site plan

  • You submit the notification with the site plan to the competent authority in writing by post or electronically by e-mail.
  • The competent authority will receive your notification and check it.
  • If further information is required, the authority will contact you.

There are no costs.

You must have submitted the notification to the competent authority at least two weeks before commissioning the system.

There is no statutory processing period.

You must have submitted the notification to the responsible authority at least 2 weeks before commissioning the system. The notification will be processed as soon as it is received.

If you do not submit the notification, or do not submit it correctly, completely or on time, you are committing an administrative offense.

None . As this is only a notification procedure, no legal action is possible on your part.