If you operate a medium-sized combustion plant, gas turbine or internal combustion engine plant, you must notify the competent authority.
As the operator of a combustion plant (medium-sized combustion plant, gas turbine and internal combustion engine plant) within the meaning of the Forty-Fourth Ordinance on the Implementation of the Federal Immission Control Act (44th BImSchV) with a rated thermal input of at least 1 MW and less than 50 MW, you are obliged to notify the competent authority in writing or electronically of the intended operation prior to commissioning.
The operation of an existing combustion plant must be notified to the competent authority in writing or electronically by December 1, 2023.
The notification must contain the following information
The notification must be submitted in writing by post or electronically to the competent authority.
Once the notification has been checked, it will be entered in a register of installations (this can also be found under the heading "Forms and information sheets"). The information contained in the register of installations is made publicly accessible in accordance with Section 36 of the 44th BImSchV and the provisions on access to environmental information (Environmental Information Act - UIG).
The notification must be submitted before commissioning a new system.
The operation of an existing installation must be notified by December 1, 2023.