The notification of the start of excavation is not an application. You only need to inform the lower excavation authority of the imminent start of excavation.
The notification of the start of excavation is intended to give the lower excavation authority sufficient time to prepare excavation monitoring measures and to check whether the period of validity of the excavation permit has expired.
If you deliberately or negligently fail to notify the start of excavation at least one week before it is carried out, you are committing an administrative offense. You can be fined up to EUR 500,000 for this. In addition, the lower excavation authority can order the excavation to be stopped.
You must notify the start of excavation if:
This also applies to a project covered by a partial excavation permit.
Digital submission of commencement notifications is not yet possible throughout Bavaria. When a location is selected, the link to the online procedure is displayed if it is already offered.
You must notify the start of excavation at least one week before the start of execution.
You generally require an excavation permit to carry out an excavation. This does not apply to smaller excavations in particular.
You can apply for a partial excavation permit if you have submitted an excavation application but have not yet received an excavation permit. This allows you to obtain a permit for individual parts of the project in advance.
You can have certain questions regarding the permissibility of your project clarified by a preliminary decision before applying for an excavation permit. This is binding for the subsequent excavation permit procedure.
If your excavation project is within the scope of a development plan that contains regulations on the permissibility, location and size of the excavation, it may not require a permit.
You must notify the start of construction in advance. This applies to the start of execution of projects requiring approval and the resumption of construction work after an interruption of more than 6 months.