Select your location for location specific information:
You can have certain questions regarding the permissibility of your project clarified by means of a preliminary decision before submitting a building application. This has a binding effect on the subsequent planning permission procedure.
This form can be submitted electronically (e.g. via a secure contact form using your user account with login via the electronic ID function or the ELSTER certificate) or handwritten and signed in paper form to the responsible authority.
This form can be submitted electronically (e.g. via a secure contact form using your user account with login via the electronic ID function or the ELSTER certificate) or handwritten and signed in paper form to the responsible authority.
This form can be submitted electronically (e.g. via a secure contact form using your user account with login via the electronic ID function or the ELSTER certificate) or handwritten and signed in paper form to the responsible authority.
This form can be submitted electronically (e.g. via a secure contact form using your user account with login via the electronic ID function or the ELSTER certificate) or handwritten and signed in paper form to the responsible authority.
You can apply for a preliminary decision on individual issues relating to your building project. You must submit this application before applying for planning permission. The subject of a preliminary decision can only be what is also the subject of the subsequent planning permission procedure.
The preliminary decision is an anticipated part of the planning permission itself. In the subsequent decision on the building permit, the lower building supervisory authority is bound by the preliminary decision insofar as it contains a regulation on the project.
The preliminary decision you have applied for will only be granted if your project is subject to approval. Furthermore, the project must not conflict with any regulations under public law.
A preliminary decision may only be issued for individual issues relating to the building project. It cannot, for example, be issued to determine compliance with all public law regulations.
Digital submission
Digital submission of applications for preliminary decisions is not yet possible throughout Bavaria. When a location is selected, the link to the online procedure is displayed if it is already available.
The fees for a preliminary decision are between EUR 40 and EUR 2,500, depending on the administrative costs incurred.
Up to half of the fees can be offset against a subsequent building permit.
There are no deadlines to be observed.
The preliminary decision is valid for three years if it is not limited to a shorter period. The period can be extended by up to two years in each case if the client applies for this in writing before the period of validity of the preliminary decision expires.
If you do not receive the requested preliminary decision, you can file an administrative court action. This must be directed at the granting of the requested preliminary decision.
An objection is not possible.
You can have certain questions regarding the permissibility of your project clarified by a preliminary decision before applying for an excavation permit. This is binding for the subsequent excavation permit procedure.
If you have applied for a building permit, you can find out about the processing status online.
You may only remove certain structures if you give prior notification of the intended removal. The removal of a structure must be notified if it is not exempt from the procedure.
You can have your building permit, partial building permit or preliminary decision extended if necessary.
You generally need a building permit to erect, modify or change the use of a facility. Only in exceptional cases is planning permission not required.
If your procedure-free project conflicts with a local building regulation, you can apply for a deviation.
If your project, which does not require a procedure or approval, contradicts other building regulations, you can apply for a deviation.
You can apply for a partial building permit if you have submitted a building application but have not yet received a building permit. This allows you to obtain permits for individual construction phases in advance.
If you have submitted the building application or the notification of the start of construction online, the declaration of compliance with the catalog of criteria can be submitted directly online by the structural engineer.
You generally need a building permit to erect, modify or change the use of a facility. Under certain conditions, your building project may be exempt from the obligation to obtain planning permission.