You can have your building permit, partial building permit or preliminary decision extended if necessary.
Building permits, partial building permits and preliminary decisions are only valid for a certain period of time.
If you are unable to start your approved project within 4 years, you can apply for an extension. If you do not receive planning permission within 4 years of receiving a preliminary building permit for the same project, you can apply for an extension of the preliminary building permit.
The extension period is up to four years, multiple extensions are possible.
An extension of the period of validity of a building permit or partial building permit is to be assessed on the basis of the same requirements as the initial granting. The project must therefore still be subject to approval at the time of the lower building supervisory authority's decision on the extension. In addition, the project must comply with public law regulations, which must be examined in the approval procedure.
This applies accordingly to the extension of the preliminary decision.
If the legal situation changes after the approval or preliminary decision has been issued, the extension must be checked against the new legal situation.
Digital submission of applications for extensions is not yet possible throughout Bavaria. When selecting a location, the link to the online procedure is displayed, if it is already offered.
Your building permit or partial building permit will expire if you have not started work on the project within 4 years of it being granted or if you have interrupted construction work for 4 years. Your application for renewal must be received by the responsible lower building supervisory authority before the expiry date. Receipt by the municipality is not sufficient to meet the deadline.
Your preliminary decision is valid for 4 years. Your application for renewal must be received by the responsible lower building supervisory authority before the expiry of the period of validity. Receipt by the municipality is not sufficient to meet the deadline.
The processing time depends on the scope and complexity of the project and the current workload of the lower building supervisory authority.
Apply for an extension in good time if it is foreseeable that the period of validity will not be sufficient.
You can appeal to the administrative court against a decision by the lower building supervisory authority regarding the extension.
If you have applied for a building permit, you can find out about the processing status online.
You generally need a building permit to erect, modify or change the use of a facility. Only in exceptional cases is planning permission not required.
You can apply for a partial building permit if you have submitted a building application but have not yet received a building permit. This allows you to obtain permits for individual construction phases in advance.
You can have certain questions regarding the permissibility of your project clarified by means of a preliminary decision before submitting a building application. This has a binding effect on the subsequent planning permission procedure.