You generally need a building permit to erect, modify or change the use of a facility. Under certain conditions, your building project may be exempt from the obligation to obtain planning permission.
This form can be submitted electronically (e.g. via a secure contact form using your user account with login via the electronic ID function or the ELSTER certificate) or handwritten and signed in paper form to the responsible authority.
This form can be submitted electronically (e.g. via a secure contact form using your user account with login via the electronic ID function or the ELSTER certificate) or handwritten and signed in paper form to the responsible authority.
This form can be submitted electronically (e.g. via a secure contact form using your user account with login via the electronic ID function or the ELSTER certificate) or handwritten and signed in paper form to the responsible authority.
This form can be submitted electronically (e.g. via a secure contact form using your user account with login via the electronic ID function or the ELSTER certificate) or handwritten and signed in paper form to the responsible authority.
In principle, exemption from approval can be granted for all structures except for special structures. However, this is only possible under certain conditions (see "Conditions"). However, even if a project is exempt from approval, it must still comply with all regulations.
Even if all the requirements for exemption from approval are met, you are not entitled to such an exemption. It is at the discretion of the local authority to decide whether or not a building permit procedure should be carried out.
The construction, modification or change of use of a building may be exempt from approval under the following conditions:
The municipality can declare that a building permit procedure is to be carried out despite these requirements being met.
First of all, please note that in the case of building applications for the construction and alteration of buildings, the building documents must be prepared by an authorized draftsman (architect, civil engineer; for smaller building projects, especially detached and semi-detached houses, also master craftsmen in the building and carpentry trades and state-certified technicians in the field of construction technology). This also applies to documents in the approval exemption procedure.
Digital submission of documents in the approval exemption procedure is not yet possible throughout Bavaria. When selecting a location, the link to the online procedure will be displayed if it is already offered.
There are no fees for the permit exemption. If the municipality informs you before the end of the one-month period that no approval procedure is to be carried out, it can charge a fee for this if it has regulated this in a municipal cost statute.
In principle, there are no time limits.
However, if you only want to start construction more than four years after the construction work has become permissible due to an approval exemption procedure, you must go through another approval exemption procedure.
If the municipality does not inform you within one month of submission of the required documents that the simplified approval procedure is to be carried out, you may commence execution. This does not apply if the municipality applies for a provisional prohibition within one month of submission of the required documents.
If your building project is exempt from approval, you are responsible for ensuring that the requirements for exemption from approval are met and that public law regulations are complied with.
Please note that you must notify the lower building supervisory authority of the start of construction at least one week in advance, even for construction projects that do not require a permit.
You must notify the start of construction in advance. This applies to the start of execution of projects requiring approval and the resumption of construction work after an interruption of more than 6 months.
You generally need a building permit to erect, modify or change the use of a facility. Only in exceptional cases is planning permission not required.
You can apply for a partial building permit if you have submitted a building application but have not yet received a building permit. This allows you to obtain permits for individual construction phases in advance.
You can have certain questions regarding the permissibility of your project clarified by means of a preliminary decision before submitting a building application. This has a binding effect on the subsequent planning permission procedure.