You must notify the start of construction in advance. This applies to the start of execution of projects requiring approval and the resumption of construction work after an interruption of more than 6 months.
This form can be submitted electronically (e.g. via a secure contact form using your user account with login via the electronic ID function or the ELSTER certificate) or handwritten and signed in paper form to the responsible authority.
??document.leistungsbeschreibung.formulare.schriftformerfordernis.0_en??
This form can be submitted electronically (e.g. via a secure contact form using your user account with login via the electronic ID function or the ELSTER certificate) or handwritten and signed in paper form to the responsible authority.
This form can be submitted electronically (e.g. via a secure contact form using your user account with login via the electronic ID function or the ELSTER certificate) or handwritten and signed in paper form to the responsible authority.
This form can be submitted electronically (e.g. via a secure contact form using your user account with login via the electronic ID function or the ELSTER certificate) or handwritten and signed in paper form to the responsible authority.
This form can be submitted electronically (e.g. via a secure contact form using your user account with login via the electronic ID function or the ELSTER certificate) or handwritten and signed in paper form to the responsible authority.
This form can be submitted electronically (e.g. via a secure contact form using your user account with login via the electronic ID function or the ELSTER certificate) or handwritten and signed in paper form to the responsible authority.
The notification of the start of construction is not an application. You only need to inform the lower building supervisory authority of the imminent start of construction.
The notification of the start of construction is intended to give the lower building supervisory authority sufficient time to prepare construction monitoring measures and to check whether the period of validity of the building permit has expired.
If you deliberately or negligently fail to notify the start of construction at least one week before the start of construction, you are committing an administrative offense. You can be fined up to EUR 500,000 for this. In addition, the lower building supervisory authority can order the suspension of construction.
You must notify the start of construction if:
This also applies to a project covered by a partial building permit and to projects that do not require a permit.
The necessity depends on the project.
The necessity depends on the project.
If the building application is submitted digitally, the structural engineer can also submit the declaration digitally using the online wizard (see service "Building project; online submission of the declaration of compliance with the catalogue of criteria" under "Related topics").
The necessity depends on the project.
If the building application is submitted digitally, the structural engineer can also submit the declaration digitally using the online wizard (see service "Building project; online submission of the declaration of compliance with the catalogue of criteria" under "Related topics").
It is not yet possible to submit notifications of the start of construction work digitally throughout Bavaria. When a location is selected, the link to the online procedure is displayed if it is already offered.
You must notify the start of construction at least one week before work begins.
As no decision is issued by the lower building supervisory authority, you cannot lodge an appeal.
If you have applied for a building permit, you can find out about the processing status online.
You may only remove certain structures if you give prior notification of the intended removal. The removal of a structure must be notified if it is not exempt from the procedure.
You must give prior notification of the commencement of use of a building structure. This does not apply to projects that do not require a procedure.
You generally need a building permit to erect, modify or change the use of a facility. Only in exceptional cases is planning permission not required.
You can apply for a partial building permit if you have submitted a building application but have not yet received a building permit. This allows you to obtain permits for individual construction phases in advance.
If you have submitted the building application or the notification of the start of construction online, the declaration of compliance with the catalog of criteria can be submitted directly online by the structural engineer.
You generally need a building permit to erect, modify or change the use of a facility. Under certain conditions, your building project may be exempt from the obligation to obtain planning permission.